ORPAON COMPRESSOR LAB

PROJECT ENGINEERING

Engineer the system around the test requirement

We adapt the load circuit, mechanical structure, DUT interface, measurement chain and software as one coordinated delivery instead of asking the test to fit a fixed bench.

Configurable engineering scope

Refrigerant circuit

Component sizing, valve strategy, expansion control and charging arrangements for the selected refrigerant and envelope.

Mechanical integration

DUT fixtures, belt drives, guarding, mobility and service access designed for the installation.

Electrical and communication

Power supply, controller protocols, clutch or actuator interfaces and remote connections as required.

Measurement system

Sensor ranges, acquisition channels, calculations and calibration access aligned with the evaluation method.

Safety and alarms

Project-specific limits, interlocks, emergency-stop responses and event records.

Software and reports

Recipes, screens, user roles, calculations, exports and reports mapped to the test workflow.

A controlled path from input to delivery

  1. 1

    Requirement review

    Clarify the DUT, test matrix, measurement method, installation and scope boundaries.

  2. 2

    Technical agreement

    Confirm system architecture, ranges, interfaces, acceptance items and deliverables.

  3. 3

    Design and build

    Develop the circuit, hardware, controls and software against the agreed configuration.

  4. 4

    Commissioning

    Verify operating points, alarms, data records and the agreed functional acceptance items.

  5. 5

    Handover

    Provide documentation, training and a defined channel for service and calibration support.

TECHNICAL INPUTS

Useful inputs for the first technical review

  • Compressor type, displacement and mounting or electrical interface
  • Refrigerant, oil and target operating envelope
  • Test items, operating points, cycle definitions and duration
  • Required measurements, accuracy targets and report format
  • Laboratory layout, chamber interfaces and available utilities

Bring us the test requirement, even if it is still a draft

We can help turn an early validation outline into a defined system scope and interface list.